Policy of
Government of West Bengal on Mini/Micro Hydro Electric Power Station upto 3 MW :-
The
high and extra high voltage industrial consumers will be allowed to set up captive power
plant through no-conventional energy sources including Mini/Micro Hydel Power Station upto
3 MW
Transmission
and wheeling of Power generated.
The facility for wheeling of Power will be provided by the utility
at a wheeling charge of 30 paise/kWh that will be revised from time to time. The wheeling
of power will be allowed to not more than one unit of the same industrial undertaking.
However, a captive power plant may be set up through a Joint Venture Company constituted
by a maximum of 2(two) industrial undertaking who would be eligible to exclusively consume
the Power from the captive Power plant in one unit each of the participating industrial
undertaking in the Joint Venture Company. For this purpose the industrial undertaking will
be required to make its own transmission lines upto nearest grid Sub-Station of the
utility along with the associated protective system as per specification of the utility
and the said transmission line shall be maintained by the generator.
Utility
will allow the power generated to be banked for a period of six month.
The
industrial undertaking will be allowed to draw power from the bank during different time
blocks of the day from energy banked by them during the corresponding time blocks.

If the
banked energy is not used for six month, the said energy will be deemed to have been sold
to the utility at a rate which shall be equivalent to weighted average of the sent-out
fuel cost of Thermal Generating Stations of the utility.
The
entire power/energy generated at the captive power plant shall be injected to/banked with
utility's grid. If the energy injected to utility's grid along with energy withdrawn from
the bank during the month is less than energy consumed by the Industrial undertaking or
the company's constituent member in case where the Captive Power Station has been set up
by a Joint Venture Company by two industrial undertaking, the utility shall deduct the
energy injected plus the energy withdrawn from the Bank during different time blocks from
the respective monthly consumption of the said consumers during the corresponding time
blocks and bill the consumers as per prevailing tariff. The amount of energy injected to
the grid along with the quantum of energy withdrawn from the Bank each month shall be
shared by the Company's Constituent Members in case of Joint Venture Project in a manner
to be intimated in writing to the utility at the beginning of each year. If the combined
maximum demand in KVA drawn by the said consumers during any month exceeds the average
power in KVA injected in the grid, such excess maximum demand shall be allocated to
constituent members of the company in case of a Joint Venture Company, in a manner to be
intimated by the company to the utility at the beginning of each year and charged to the
consumers as per prevailing tariff of the utility. The industrials undertakings shall have
to ensure payment of AMGR as per power supply agreement executed by them with the
utilities.
A
consumer having solar P.V. installation will be allowed to inject his surplus energy to
the grid with the banking facility as admissible for industrial undertaking having captive
Hydel Power Station upto 3 MW.
There
will be no provision of sale of power by the industrial undertaking to any third party.
However, a captive power plant set-up through a joint venture company constituted by a
maximum of 2(two) industrial undertakings will be eligible to exclusively consume the
Power from the captive power plant in one unit each of the participating industrial
undertakings in the Joint venture Company.
Captive
Power can be wheeled through the system of one utility only.

Policy in
Respect of Captive Power Plants Utilising Conventional Fuel :-
New
industries may be allowed to set up Captive Power Plant for continuous running provided
the same is not connected to the Power Utility's Grid and there is no third party sale. If
such captive generation is through installation of diesel generator se, control of noise
pollution must be as per stipulations of the Pollution Control Board.
Already
operating industries wishing to switch over to captive generation-party or fully, may be
allowed to set up Captive Generation Plant provided such plant is not connected to the
Power Utility's Grid and there is no third party sale.
Environment
clearance should be obtained from the West Bengal Pollution Control Board and Environment
Department of the State Government.
Consumers
drawing backup power or partial power from Power Utility shall pay monthly demand charge
on contract demand at double the normal demand charge rate provided the actual drawal is
less than the contract demand. In the event actual demand in a month exceeds the contract
demand the excess demand shall be charge at three times the normal charge rate.
Electricity
Duty will be payable under the Bengal Electricity Duty Rules as amended from time to time.
Metering arrangement should be made for recording consumption of power generated in the
Captive Plants.
Industrial
units may apply to the West Bengal State Electricity Board for clearance u/s-44 of the
Electricity (Supply) Act, 1948, after obtaining clearance from West Bengal Pollution
Control Board and the Environment Department, Government of West Bengal. Before given
consent u/s-44 (1) of the Act, the WBSEB shall consult Central Electricity Authority in
cases where the capacity of the Captive Plant exceeds 25 MW.

|